Orange Barrel Report for the Week of October 1, 2023 | City of Santa Fe

Orange Barrel Report for the Week of October 1, 2023

29 Sep, 2023

New


Rodeo Road (JDR Construction) will begin working on repaving Rodeo Road between Camino Carlos Ray and Yucca Road on October 2, 2023. The road will be closed one direction at a time, and traffic will be detoured to Zia Road. The project is projected to be completed on October 11, 2023. Please contact Mark Brooks at 505-955-2404 or mebrooks@santafenm.gov with any questions.  

 

Ongoing


W. Alameda (The City of Santa Fe Public Works Department) The replacement culvert is being designed and constructed to meet the future needs of the improved roadway to be built during the larger West Alameda Capital Improvement Project.

The replacement culvert and channel protection systems are being installed simultaneously. The current rough estimate for the reopening of the road is October 2023. The road closures at Calle Nopal and the Siler Roundabout will remain in place until the repairs are fully completed. Please allow extra travel time if navigating around the detours and seek alternate routes whenever possible.

Thank you to all our residents for their patience as we complete this project and make necessary improvements to support the safety of this culvert for years to come!

5520 Wellness Way (Essential Utilities) will be running power across 5520 Wellness Way across the Presbyterian Hospital. Road closures, detours, and message boards are in place. Please seek an alternative route when possible. Work began on September 18, 2023, and is scheduled to be completed on October 02, 2023. Please contact Teddy Padilla at 505-231-4794 should you have any questions.

Camino de la Familia and Paseo de Peralta (Insituform) will install new liners inside approximately 16,000 feet of sanitary sewer pipe. Insituform will utilize a trenchless technology process where the new liners will be pulled through the existing sewers line by pulling the line through the existing manhole openings, which means no excavation of roads is required. Starting on October 3, 2023, the sanitary sewer line work will start at the intersection of Camino de La Familia and Paseo de Peralta to the intersection of Alarid St. Once completed. We will move down Alarid St. to the intersection of Mercer St. and Onate Rd. Signs will be posted to alert the public of their presence. The project is anticipated to be completed by October 2023. Work will start every evening at 7:00 p.m. and continue through the night until 7:00 a.m. Traffic access through the work sites will be delayed, and you should seek alternate routes. Contact Stan Holland, P.E., at 505-955-4637 or Fred Heerbrandt, P.E., at 505-955-4623 should you have any questions.

Agua Fria/South Meadows (The City of Santa Fe Public Works Department) Public Works Department will begin the work on the Agua Fria/South Meadows Intersection improvements. The project will consist of adding turning bays on Agua Fria and South Meadows and signal improvements. Work started on July 31, 2023, and the project is projected to be completed by February 2024. There will be traffic delays, and you should seek alternate routes when possible. Please contact Mark Brooks at 505-955-2404 or mebrooks@santafenm.gov should you have any questions.

Ragle Park Ballfield #2 (The City of Santa Fe) The City of Santa Fe will be starting our re-surfacing project. The Parks Division will be working with Hellas Construction, Inc. to install a new synthetic turf field at Ballfield #2. Construction work started on July 31, 2023, and is expected to be completed by October 2023. We will be closing the park trail on the north side of the ballfield and will have a detour posted on-site. Please contact Scott Overlie at saoverlie@santafenm.gov or 505-231-6194 should you have any questions.

Cerro Gordo Open Space (The Nature Conservancy), the Nature Conservancy’s - Santa Fe Canyon Preserve.  The second phase of an ongoing project, which includes earthwork and fencing, began on November 16, 2022.  All work will be performed on Nature Conservancy property, but access is via the City Parks Department’s – Cerro Gordo Open Space trailhead parking area.  The second phase of the project has started and is ongoing now through the summer months. The preserve will remain open. The construction site is temporarily fenced.  Please contact Scott Overlie at saoverlie@santafenm.gov or 505-231-6194 with any questions.

Beckner Rd (Sparling Construction) striping of the road is 90% complete, but road closures are still needed while crews work on finalizing the landscaping. We are projecting this project to be completed by September 2023. The road will continue to be closed between Richards Avenue and Wellness Way. Message Boards and detours are in place at the closures – please seek an alternative route. Please contact Teddy Padilla at 505-231-4794 should you have any questions.

Siringo Road and Saint Michaels Drive (Blue Line Construction) The Rail Trail will be closed on August 28, 2023, through October 6, 2023, between Siringo Road and Saint Michaels Drive as a new sanitary and sewer connection line will be installed along with the rail trail realignment in conjunction for the new Cerro De Norte subdivision. Please contact Blue Line Construction at 505-259-1148 should you have any questions. 

Guadalupe St. (The City of Santa Fe Public Works Department) The work on the Guadalupe St. Reconstruction Project will begin September 11, 2023. The project is a complete reconstruction of Guadalupe from Alameda to Paseo De Peralta. The project will last for the next 18 months and will include closures, lane shifts, and flagger operations. The first phase, beginning on the 11th of September, will be the reconstruction of the Bridge deck at Guadalupe and Alameda. Guadalupe will be closed in both directions at the bridge, and detours will be in place. There will also be lane shifts on Alameda during this time. This phase of construction is expected to last for 6 weeks. Please seek alternate routes and expect delays. Contact Mark Brooks at 505-955-2404 or mebrooks@santafenm.gov should you have any questions.

200 Murales Road (City of Santa Fe Streets Division) is repairing and rebuilding a sidewalk at 200 Murales Road. The second phase of this project will begin on September 25, 2023, and is projected to be completed by October 27, 2023. Please proceed with caution. Contact Apollo Hernandez at 505-365-8855 should you have any questions.

Isabella Sharpe (Izzy), Constituent Services Manager
505-955-6329 ilsharpe@santafenm.gov

Share