New Projects
113 Valencia Rd (City of Santa Fe - Transmission and Distribution) will be installing a new water service at 113 Valencia Rd the week of October 22, 2023. The road will be closed - please seek an alternative route. Please contact Randy Lopez at 505-955-4246 should you have any questions.
126 W Buena Vista (City of Santa Fe - Transmission and Distribution) will be working at 126 W. Buena Vista doing some asphalt road patching the week of October 22, 2023. The road will be closed - please seek an alternative route. Please contact Randy Lopez at 505-955-4246 should you have any questions.
Arroyo de los Pinos at Practilliano Dr and Camino Chueco (Franco’s Trees and Landscaping) will be in the arroyo, cleaning out vegetation and thinning trees to help with the proper flow of stormwater. The work is scheduled to begin in the next week and should be completed by the end of the first week of November 2023. Please contact Andrew Wright at 505-955-2133 or afwright@santafenm.gov should you have any questions.
Alameda St., just east of Paseo de Peralta (City of Santa Fe Parks Division), will be removing a large cottonwood tree that has fallen over into the Santa Fe River Park. The work will start on October 30, 2023, and will be completed that same day. Traffic is not expected to be affected. Please contact Skyler Nielsen at 505-469-6688 or snielsen@santafenm.gov with any questions.
Ongoing Projects
Arroyo de los Pinos at Luisa & St. Francis (Franco’s Trees and Landscaping) will be in the arroyo, cleaning out dead branches to help with the proper flow of stormwater. The work is scheduled to be completed in the month of October 2023. Please contact Andrew Wright at 505-955-2133 or afwright@santafenm.gov should you have any questions.
Plaza Central (EMCO Construction) Will begin reconstructing sidewalk ramps and re-paving Plaza Central between Paseo Del Sol West and Contenta Ridge. There will be flaggers and lane shifts in place. There will also be some access roads that will be closed. The work will begin the week of October 16, 2023, and should last until October 27, 2023. Please Call Mark Brooks at 505-955-2404 or mebrooks@santafenm.gov with any questions.
Alarid St and Camino Sierra Vista (Insituform) will install new liners inside approximately 16,000 feet of sanitary sewer pipe. Insituform will utilize a trenchless technology process where the new liners will be pulled through the existing sewers line by pulling the line through the existing manhole openings, which means no excavation of roads is required. Starting on October 7, 2023, the sanitary sewer line work will start at the intersection of Alarid and Camino Sierra Visita. Once completed, we will move down to the intersection of Mercer St and Onate Rd. Signs will be posted to alert the public of their presence. The project is anticipated to be completed by October 2023. Work will start every evening at 7:00 p.m. and continue through the night until 7:00 a.m. Traffic access through the work sites will be delayed, and you should seek alternate routes. Contact Stan Holland, P.E., at 505-955-4637 or Fred Heerbrandt, P.E., at 505-955-4623 should you have any questions.
Agua Fria/South Meadows (The City of Santa Fe Public Works Department) Public Works Department will begin the work on the Agua Fria/South Meadows Intersection improvements. The project will consist of adding turning bays on Agua Fria and South Meadows and signal improvements. Work started on July 31, 2023, and the project is projected to be completed by February 2024. There will be traffic delays, and you should seek alternate routes when possible. Please contact Mark Brooks at 505-955-2404 or mebrooks@santafenm.gov should you have any questions.
Cerro Gordo Open Space (The Nature Conservancy), the Nature Conservancy’s - Santa Fe Canyon Preserve. The second phase of an ongoing project, which includes earthwork and fencing, began on November 16, 2022. All work will be performed on Nature Conservancy property, but access is via the City Parks Department’s – Cerro Gordo Open Space trailhead parking area. The second phase of the project has started and is ongoing now through the summer months. The preserve will remain open. The construction site is temporarily fenced. Please contact Scott Overlie at saoverlie@santafenm.gov or 505-231-6194 with any questions.
Beckner Rd (Sparling Construction) striping of the road is 90% complete, but road closures are still needed while crews work on finalizing the landscaping. We are projecting this project to be completed by October 2023. The road will continue to be closed between Richards Avenue and Wellness Way. Message Boards and detours are in place at the closures – please seek an alternative route. Please contact Teddy Padilla at 505-231-4794 should you have any questions.
Guadalupe St. (The City of Santa Fe Public Works Department) The work on the Guadalupe St. Reconstruction Project will begin September 11, 2023. The project is a complete reconstruction of Guadalupe from Alameda to Paseo De Peralta. The project will last for the next 18 months and will include closures, lane shifts, and flagger operations. The first phase will be the reconstruction of the Bridge deck at Guadalupe and Alameda. Guadalupe will be closed in both directions at the bridge, and detours will be in place. There will also be lane shifts on Alameda during this time. This phase of construction is expected to last for six weeks. Please seek alternate routes and expect delays. Contact Mark Brooks at 505-955-2404 or mebrooks@santafenm.gov should you have any questions.
200 Murales Road (City of Santa Fe Streets Division) is repairing and rebuilding a sidewalk at 200 Murales Road. The second phase of this project will begin on September 25, 2023, and is projected to be completed by October 27, 2023. Please proceed with caution. Contact Apollo Hernandez at 505-365-8855 should you have any questions.
Upcoming Projects
Marc Brandt Park at Siringo Rd & Richards Ave (EMCO of Santa Fe) will be clearing sediment and vegetation from the southwest end of Marcel “Marc” Brandt Park to help with the proper flow and drainage of stormwater. The work is scheduled to begin in the first week of November 2023 and should take less than one week once started. The work will involve traffic calming on Richards Ave northbound between the two lanes of Siringo Rd, dates to follow. Please contact Andrew Wright at 505-955-2133 or afwright@santafenm.gov should you have any questions.
Tierra Contenta Trail (EMCO of Santa Fe) will be installing a storm drain, repaving the trail, and seeding the area. The work is scheduled to begin in the first week of November 2023 and should be completed within that month. The work will involve closing a portion of the trail and dates to follow. Please contact Andrew Wright at 505-955-2133 or afwright@santafenm.gov should you have any questions.
Henry Lynch Road (JDR Construction) will be re-paving Henry Lynch Road starting October 23, 2023, and should be completed by October 27, 2023. The road will be closed from 8:00 am to 6:00 pm. detours will be in place - please seek an alternate route. Please contact Mark Brooks at 505-955-2404 or mebrooks@santafenm.gov should you have any questions.
Isabella Sharpe (Izzy)
Constituent Services Manager
505-955-6329
ilsharpe@santafenm.gov