New
Contractor: Jaynes Corp
Location: CSV Cancer Center St. Michael’s
Description: Jaynes Corp will start doing the Median work for the Cancer Center on St. Michael’s. As the work goes on, Jaynes Corp will have lane closures. All traffic controls will be set up and in place. Please expect delays. Work will start on Sept. 16 and end on Sept. 17. If all goes according to plan, the job's estimated end date will be 10/25/24.
Contact: Ryan M. Gomez rmgomez@santafenm.gov
Ongoing
Hyde Park: NMDOT is doing a major project on Hyde Park Road. This is not a city project. The road will be closed six days a week (open on Sundays) until early October. For more updates about the project, visit here.
Contractor: A & S Plumbing
Location: Jaguar Dr. by State Police
Description: A & S Plumbing will install a new water line on Jaguar Dr. between the State Police entrances. Work is scheduled to start Monday, Sept. 9, and end Friday, Sept. 13. The road will be closed at Jaguar Dr. and Cerrillos Rd. Detours will be in place. Expect delays. The detour route will be through Camino Entrada to South Meadows Rd.
Contact: Ryan M. Gomez rmgomez@santafenm.gov
Contractor: EMCO
Location: Arroyo de los Pinos behind Herb Martinez Park
Description: EMCO will install gabion baskets in the arroyo for erosion control. Work began July 15 and is expected to take several months. The entry point will be at Santa Clara Drive and Alamosa Drive. Traffic control and signage will be in place with minimal impact on traffic.
Contact: Jimmie Gallegos, jgallegos1@santafenm.gov
Contractor: EMCO
Location: Agua Fria/South Meadows
Project Description: The Public Works Department is constructing the Agua Fria/South Meadows Intersection Improvements Project. The project includes adding turning bays on Agua Fria and South Meadows and improving the signal. Traffic delays will occur, and you should seek alternate routes when possible. The detour is from South Meadows to Rufina and Jemez Rd. Signage is in place—project completion target date: December 2024.
Contact: Kody Keelin kwkeelin@santafenm.gov
Contractor: EMCO
Location: Paseo Real
Description: EMCO will remove existing roadway surfacing and install new pavement and pavement markings from #11 Paseo Real to Huey Rd. Work is scheduled to begin the week of Sept. 16. Flagmen will direct traffic through the construction zone. Expect delays and loose gravel during the re-paving process. Construction is expected to last three to four weeks.
Contact: Kody Keelin kwkeelin@santafenm.gov
Contractor: INTERA Incorporated
Location: Camino Porvenir, Fayette St, and between the Acequia Trail and Potencia St
Project Description: On behalf of PNM and under the oversight of NMED PSTB, INTERA is conducting environmental investigation activities along the City of Santa Fe-owned Acequia Trail and in the roadways along Camino Porvenir (near the intersection with Baca St) and Fayette St. Traffic control and signage will be in place, including necessary detours. Activities include drilling and installing three monitoring wells (one per location). Drilling will begin on Tuesday, Oct. 1, and continue until mid-to-late Oct. 2024. From then on, drilling work is scheduled to start at 8 am. Monday through Friday and will conclude at approximately 5 pm each day.
Contact: Jim Gibb (PSTB Project Manager), jim.gibb@env.nm.gov or E.J. Anderson (PNM Project Manager), ej.anderson@pnmresources.com
Contractor: The Nature Conservancy
Location: Cerro Gordo Open Space
Project Description: The second phase of an ongoing project includes earthwork and fencing. All work will be performed on Nature Conservancy property, but access is via the City Parks Department’s Cerro Gordo Open Space trailhead parking area. The preserve will remain open. The construction site is temporarily fenced.
Contact: Scott Overlie at saoverlie@santafenm.gov or 505-231-6194
Contractor: GM Emulsion
Location: Guadalupe St.
Project Description: The work on the Guadalupe St. Reconstruction Project began in January
2024. The project is a complete reconstruction of Guadalupe St. from Alameda to Paseo De Peralta. The project will last for the next 18 months and will include closures, lane shifts, and flagger operations. The project is now in phase II, removing the sidewalk, curb, and gutter from West San Francisco St to Paseo De Peralta, along with the median curb replacement at the intersection of Guadalupe & Paseo De Peralta. Work will include removing sidewalks and curb ramps; sidewalks will be closed during construction with pedestrian detours—project completion target date: June 2025.
Contact: kwkeelin@santafenm.gov
Contractor: GM Emulsion and McDade-Woodcock
Location: Beckner Road and Richards Avenue
Project Description: Message boards and Temporary Traffic Control at the Beckner and Richards Ave intersection will be in place. This is for public Safety. Beckner Rd. Shall remain as Right-In and Right-out access only during this work. Left turn movements from Beckner Rd (North) or Mission Bend Rd will not be permitted. (South) until the signals are nearing completion. During the construction, motorists from the Mission Bend Sub-Division, including the school, who wish to take a left turn and head south on Richards Ave., will temporarily use the Mission Bend (North) intersection. Right-in/right-out access to Mission Bend (South) will be permitted.
Contact: Ryan M Gomez rmgomez@santafenm.gov
Contractor: GM Emulsion
Location: Rail Trail between Alta Vista St. and I-25
Project Description: Portions of the Rail Trail will be closed from Sept. 9 – Sept. 20, as GM Emulsion will perform trail maintenance and patchwork. Suitable detours will be provided for closed areas.
Contact: Scott Overlie, saoverlie@santafenm.gov