Disclaimer: The information in the Orange Barrel report is compiled based on the best available information and is subject to change without notice.

This page was updated on Friday, May 23, 2025, at 3:54 pm


 

NEW PROJECT
Location: City-owned lot across 4808 Agua Fria Street.
Contractor: Franco’s Trees and Landscaping
Description: The placement of a cable to prevent entry into the Santa Fe River. Work is to be done the week of May 26th and will be completed in a day.  
Contact: Jimmie Gallegos, jgallegos1@santafenm.gov

 

NEW PROJECT
Location: Holding ponds behind Santa Fe Spa
Contractor: Franco’s Trees and Landscaping
Description: Dredging of two holding ponds behind the Santa Fe Spa. Work is to begin 5/27/2025 and is anticipated to take 2-3 weeks, and will have no impact on traffic.
Contact: Jimmie Gallegos, jgallegos1@santafenm.gov

PROJECT ONGOING AS SCHEDULED
Location: Morelia St. @ Letrado St. Intersection
Contractor:  Eagle Concrete Construction and Excavation LLC.
Description:  Construction at the intersection of Morelia and Letrado St involving a Valley gutter install and rebuild of the east sidewalk corner. The Road will be temporary closed to thru traffic during the demolition and concrete pour. Work began on 5-12-25 and will continue thru 5-30-25. All Traffic control and detours are in place. Construction duration is subject to change.
Contact: Apollo Hernandez, ajhernandez@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED
Contractor: SF Brown Inc  
Description: Zia Station Public Infrastructure project.  
GALISTEO ROAD CLOSED BETWEEN ZIA RD. AND CALLE LUMINOSO
ACCESS TO ZIA RD RAILRUNNER STATION VIA TEMPORARY ACCESS ROAD OPPOSITE CALLE LUMINOSO.
Single lanes of travel, both eastbound and westbound on Zia Rd. between Vela St. and Galisteo.  
Sidewalk on north side of Zia will be open from Candelero to St. Francis  
Sidewalk on south side of Zia from Vela to Galisteo remains closed
Repaving of Zia Road has commenced.
INITIAL PHASE OF ZIA ROAD REPAVING WILL BEGIN WEEK OF MAY 19 - 23
Turn bays and inside lanes (lanes closest to the medians) of Zia Rd – both eastbound and westbound will be paved with an initial 3” lift of asphalt beginning Tuesday, 5/20
Upon completion, traffic will be diverted to these inside lanes.
Caution is urged as there will be significant grade change between the new and existing asphalt levels – PLEASE SLOW DOWN
Galisteo Road realignment work between Calle Luminoso and Zia to include:
PNM Backbone trenching
Gas line installation
Speed on Zia Rd between St. Francis and Brilliante reduced to 25 mph
Please be cautious in this area. SLOW DOWN and DO NOT STOP ON TRAIN TRACKS!  
Contact: Merritt Brown, merritt@sfbrown.com, Ryan Gomez, rmgomez@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED
Location: Arroyo Los Chamisos North Fork - Site 2
Contractor: EMCO    
Description: EMCO will be conducting erosion control and bank repair work. Work started Nov. 4th and is expected to be completed by June 15. The entry point will be off Avenida de las Campanas, with the staging area at Santa Clara Drive and Alamosa Drive. All work will be done during school hours from 9 a.m. to 3 p.m. Traffic control and signage will be in place with minimal impact on traffic.  
Contact: Jimmie Gallegos, jgallegos1@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED
Location: Agua Fria/South Meadows
Contractor: EMCO 
Description: The Public Works Department is constructing the Agua Fria/South Meadows Intersection Improvements Project. The project includes adding turning bays on Agua Fria and South Meadows and improving the traffic signals, sidewalk, and ADA ramps. Two lanes of travel will remain open for Agua Fria (west/east) and one lane of travel for South Meadows (north/south). Traffic delays will occur, and you should seek alternate routes when possible. The detour is from South Meadows to Rufina and Jemez Rd. Signage is in place.  
The project anticipated completion target date is June 2025. 
Contact: Kody Keelin, kwkeelin@santafenm.gov or Kevin Harrison, kharrison@espmerc.com

 

PROJECT ONGOING AS SCHEDULED
Location: Guadalupe St.
Contractor: GM Emulsion  
Description: The work on the Guadalupe St. Reconstruction Project began in January 2024. The project is a complete reconstruction of Guadalupe St. from Alameda to Paseo De Peralta. The project will include closures, lane shifts, and flagger operations.  
The project is now in Phase 6. We are now working on the installation of the new median curb and gutter and new asphalt paving. Starting Monday April 28, the South bound lane on Guadalupe St will be closed at the intersection Guadalupe St and West Alameda. Detour will be South Sandoval to Montezuma West. The closure is needed for new asphalt paving.  
The northbound lane on Guadalupe St is closed at the intersection of Alameda St and Guadalupe St. The Detour is Alameda West to Sandoval North to Johnson St. 
Please follow detour signage that are in place if you must use Guadalupe St. Please drive safely.    Project completion target date: Summer 2025.
Contact: Romella Glorioso-Moss, rsglorioso-moss@santafenm.gov or Mark Brooks, mark@gmemulsion.com
Click here for Construction Updates
Project Update: Guadalupe Construction Overview (Public Works)

 

PROJECT ONGOING AS SCHEDULED
Location: Old Pecos Trail from Cordova Rd. to Calle Medico
Contractor: GM Emulsion
Description:  Paving and Striping are complete. Concrete construction to continue, pending weather and varying factors that may affect schedules. Efforts will be made to minimize disruption to traffic and pedestrians however; traffic patterns may have minor alterations as needed.  Please use caution in the area.  Your patience and compliance with Traffic Control Signage is greatly appreciated.
Contact: mpesquibel@santafenm.gov.  

 

PROJECT ONGOING AS SCHEDULED
Location: Santa Fe Railyard Irrigation
Contractor: Accent Landscaping
Description: The renovation of the irrigation system at the Railyard Park includes a complete replacement of the system. This includes work to restore the function of the cistern system that collects precipitation from the building’s roofs for use in he landscape. The system will include all new piping, valves, and irrigation heads throughout the park. The design is specialized to supply supplemental water to natural precipitation and allow the existing vegetation to flourish. The new design approach and efficient head spacing are estimated to reduce water demands by 47%. The new system will be significantly easier to maintain be consolidating all of the irrigation into a single distribution network, reducing the number of heads while maintaining uniform water application, and replacing the operation system with a smart controller that is easily adjustable with changing climate conditions. The system will primarily use the water collected in the cisterns and only use a domestic water source when the harvested water is exhausted. The construction will be sequenced so that the park will remain partially open and allow operation of the existing system to avoid periods of no irrigation. Construction is anticipate to be completed in August, 2025.
Contact: Josh Bohlman, jbohlman@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED
Location: Sandoval Parking Garage
Contractor: Davenport Construction
Description: Davenport's subcontractor will be patching and painting the exterior of the Sandoval Garage. During this time, certain sidewalks, entrances, and exits will be temporarily closed. However, at least one entrance and one exit will remain open at all times. Additionally, the garage will undergo re-striping of all parking spots, resulting in certain floors being closed. At least two parking floors will remain open while this work is being carried out.
Shutdown Dates:
Sidewalks-TBD
Entrance/Exits-TBD
Re-Striping-TBD 
Contact: Josh Bohlman, jbohlman@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED
Location: Rufina from Zafarano to Calle Atajo
Contractor: GME General Building LLC.
Description: Paving and striping are complete, roadway symbols will be placed soon as weather allows. Use caution in the area. Pedestrian traffic and vehicular traffic may see varying patterns with effort made to minimize disruption but maximize completion of the project in a timely manner.  
Contact: Marcos Esquibel, mpesquibel@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED
Location: Rancho Siringo Rd & Rancho Siringo Dr.
Contractor: Sub Surface Contracting 
Description: Sub Surface will install a new water main on Rancho Siringo Rd and Rancho Siringo Dr. Started 12-9-24 and going on until approximately MAY 2025. The road will be closed to traffic, but the public who lives in the area will still have access to their homes. All traffic controls will be in place, including detour routes. The contractor will have steel plates in case of any emergency and will always have access to get in and out of the job site. Sub Surface are in the process of transferring all services to new line. Once done, they will begin the asphalt process of all work.  
Contact: Ryan M. Gomez, rmgomez@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED
Location: Sandoval from Alameda to Grant and Palace from Grant to Sheridan
Contractor: GME General Building LLC.
Description: Loop detectors to be installed periodically, as scheduling allows. Use caution in the area.
Contact: Marcos Esquibel, mpesquibel@santafenm.gov

NO UPDATES RECEIVED
Location: St. Michaels Ave, Santa Fe
Contractor: NM Licensed Contractor
Description: The Old St Mike’s well is an unused, abandoned, and capped well next to the existing St Mike’s water supply well. The Old St Mike's well will be plugged and abandoned as part of the City’s ongoing effort to improve and protect our groundwater supply. The City Water Division has obtained an approved permit from the New Mexico Office of the State Engineer and hired a New Mexico-licensed contractor to perform the work. A safety plan is in place. Required work will be performed during daylight hours only starting May 21st. The project will take approximately two days.   There will be minimal to no disruption to traffic as all work will be performed on City property.  Contact: Danny Valenzuela, davalenzuela@santafenm.gov; Jonathon Montoya, jmmontoya@santafenm.gov or  Bill Schneider, whschneider@santafenm.gov

 

NO UPDATES RECEIVED
Location: St. Michaels Ave, Santa Fe
Contractor: NM Licensed Contractor
Description: The Old St Mike’s well is an unused, abandoned, and capped well next to the existing St Mike’s water supply well. The Old St Mike's well will be plugged and abandoned as part of the City’s ongoing effort to improve and protect our groundwater supply. The City Water Division has obtained an approved permit from the New Mexico Office of the State Engineer and hired a New Mexico-licensed contractor to perform the work. A safety plan is in place. Required work will be performed during daylight hours only starting May 21st. The project will take approximately two days.   There will be minimal to no disruption to traffic as all work will be performed on City property.  Contact: Danny Valenzuela, davalenzuela@santafenm.gov; Jonathon Montoya, jmmontoya@santafenm.gov or  Bill Schneider, whschneider@santafenm.gov

 

NO UPDATES RECEIVED
Location: 206 Mckenzie St.
Contractor: True North Builders LLC.  
Description: True North Builders LLC will build the house at 206 Mckenzie St. Due to the small area, the road must be closed, and they must demo the building safely. All detours will be set up through the end of June 2025. The area will need to be fenced off from the public. All utilities and the curb in front of the property will be redone.   
Contact: Ryan M. Gomez, rmgomez@santafenm.gov

 

NO UPDATES RECEIVED
Location: Calle Atajo (Airport to Rufina)
Contractor: EMCO of Santa Fe, LLC
Description: Calle Atajo Speed Tables (Phase 2)
Placement of Seven Speed Tables on Calle Atajo between Airport and Rufina.  This work has been postponed due to weather and is now planned for the week of May 12, 2025. (The first phase involved placement of speed tables north of Rufina.)  
Contact: Kevin Harrison of EMCO, kharrison@espmerc.com