Subscribe to the Orange Barrel Report

* indicates required
() -(###) ###-####
Choose List
Ongoing

 

Contractor: AAC
Location: 609 Paseo de Peralta
Description: Emergency sewer repair work at 609 Paseo De Peralta will start today and continue for several days. Today, the road will be closed for a few hours only to inspect the area to gauge what type of materials and equipment will be needed for this job since the repair will require a trenching greater than eight feet. The road will be closed until the job is complete.
Contact: Benjamin Sandoval, basandoval@santafenm.gov

Contractor: Jaynes Corp
Location: CSV Cancer Center St. Michael’s
Description: Jaynes Corp will start doing the Median work for the Cancer Center at St. Michael’s. As the work goes on, Jaynes Corp will have lane closures. All traffic controls will be set up and in place. Please expect delays. If all goes according to plan, the job's estimated end date will be Oct. 25.
Contact: Ryan M. Gomezrmgomez@santafenm.gov

Contractor: Daniel’s Landscaping and Construction 
Location: Rio Vista Place 
Project Description: Daniel’s will haul out trees left behind by PNM, exposing powerlines. They will also cut any downed branches in the drainage channel upstream and downstream. Work will be conducted Nov. 16-17.  
Contact: Jimmie Gallegos, jgallegos1@santafenm.gov  

Contractor: EMCO 
Location: Arroyo los Chamisos North Fork - Site 2  
Description: EMCO will be conducting erosion control and bank repair work. Work will begin Nov. 4th and is expected to take several months. The entry point will be off Avenida de las Campanas, with the staging area at Santa Clara Drive and Alamosa Drive. All work will be done during school hours from 9 a.m. to 3 p.m.Traffic control and signage will be in place with minimal impact on traffic. 
Contact: Jimmie Gallegos, jgallegos1@santafenm.gov 
 

Contractor: EMCO
Location: Arroyo de los Pinos behind Herb Martinez Park
Description: EMCO will use this area as a staging area for equipment and supplies. Work began July 15 and is expected to take several months. The entry point will be at Santa Clara Drive and Alamosa Drive. Traffic control and signage will be in place with minimal impact on traffic.
Contact: Jimmie Gallegos, jgallegos1@santafenm.gov

Contractor: EMCO
Location: Agua Fria/South Meadows
Project Description: The Public Works Department is constructing the Agua Fria/South Meadows Intersection Improvements Project. The project includes adding turning bays on Agua Fria and South Meadows and improving the signal. Traffic delays will occur, and you should seek alternate routes when possible. The detour is from South Meadows to Rufina and Jemez Rd. Signage is in place. The project completion target date is December 2024.
Contact: Kody Keelinkwkeelin@santafenm.gov

Contractor: Davenport Construction Management, LLC 
Location: Closson Street Pedestrian Bridge, bridge spans the Santa Fe River from Closson Street to Alameda Street. 
Project Description: Demolition and removal of the existing pedestrian bridge due to structural failure. Work to begin Nov. 4 and should be completed Nov. 29. Road closures to include Alto Street Alley between Barela Street and Closson Street., Closson Street between Alto Street and Alto Street Alley. Additional closure of the Santa Fe River Trail 20 feet on each side of the trail at the intersection of the location of the pedestrian bridge on the Alameda Street side of the river. Detours will be posted for all closures.  
Contact: Scott Overlie at saoverlie@santafenm.gov or 505-231-6194 

Contractor: Full Circle 
Location: River trail from Siler Bridge to Frenchy’s Park 
Project Description: Removal and thinning of invasive species, clearing of bar ditch, and minor repairs from Siler Bridge to Frenchy’s Park. Work began Oct. 23 and will last through November.  

Contact: jgallegos1@santafenm.gov 

Contractor: INTERA Incorporated  
Location: Camino Porvenir, Fayette St, and between the Acequia Trail and Potencia St  
Project Description: On behalf of PNM and under the oversight of NMEDPSTB, INTERA is conducting environmental investigation activities along the City of Santa Fe-owned Acequia Trail and in the roadways along Camino Porvenir (near the intersection with Baca St) and Fayette St. Traffic control and signage will be in place, including necessary detours. Activities include drilling and installing three monitoring wells (one per location). Drilling began on Monday, Oct. 14, and will continue until Monday, Dec. 2, 2024. Drilling work is scheduled to start at 8 a.m. Monday through Friday and will conclude at approximately 5 p.m. each day. Drill rig breakdowns may occur and cause a delay in the drilling operation. 
Contact: Michale Leger (PSTB Project Manager), michael.leger@env.nm.gov, Austin Hanson (INTERA Incorp.), AHanson@intera.com, or E.J. Anderson (PNM Project Manager), ej.anderson@pnmresources.com
 

Contractor: GM Emulsion
Location: Guadalupe St.
Project Description: The work on the Guadalupe St. Reconstruction Project began in January 2024. The project is a complete reconstruction of Guadalupe St. from Alameda to Paseo De Peralta. The project will include closures, lane shifts, and flagger operations. The project is now in phase 3; the week of Nov. 18 will have a new traffic pattern; both north and southbound lanes will now be shifted to the westside of Guadalupe for the start of the removal of curb and gutter, sidewalks, and drop inlets.  The traffic signals at the intersections of West San Francisco Street and North Guadalupe Street, along with the intersection of Catron Street and North Guadalupe Street, have been removed; a four-way stop sign is now in place. Nov.18 Paseo De Peralta will have a lane closure on the westbound to replace ADA ramps.  —project completion target date: June 2025. 

Contact: kwkeelin@santafenm.gov
Construction Updates: https://santafenm.gov/public-works/engineering-division/capital-projects-section/guadalupe
Project Update: Guadalupe Construction Overview (Public Works)

Contractor: GM Emulsion and McDade-Woodcock
Location: Beckner Road and Richards Avenue
Project Description:  The City of Santa Fe’s contractors continue to make progress on the intersection improvements.  Temporary Traffic Control at the Beckner and Richards Ave intersection will remain in place through the completion of the project, with restricted left turns at that intersection. Depending on the weather, beginning Monday, Nov. 18, through Friday, Nov. 29, Temporary Traffic Control at the Mission Bend and Richards Ave intersection will be installed to support the installation of curb ramps and stoplight poles.  Access to the south entrance to Mission Bend from northbound Richards Ave will be accessible.  Access to the south entrance to Mission Bend from southbound Richards Ave remains closed.  The contractor requests motorists proceed with caution through the work zone.

Contractor: Seeds of Wisdom 
Location: Arroyo that runs behind Fire Station #3 at Ashbaugh Park 
Project Description: Thinning of invasive elms. 
Contact: Jimmie Gallegos, jgallegos1@santafenm.gov 

Contractor: Seeds of Wisdom
Location: West Alameda
Project Description: Seeds of Wisdom is thinning trees along the Santa Fe River from the Gonzales bridge to St. Francis. All trees being cut are invasive species. Temporarily, temporary access to the river trail will sometimes be provided for high-risk trees being cut. All work will be conducted during school hours.. Flagmen will be in place to direct traffic through the work zone when necessary. Work will continue through November.
Contact: Jimmie Gallegos, jgallegos1@santafenm.gov.

Contractor: True North Builders LLC. 
Location: 206 Mckenzie St. 
Project Description: True North Builders LLC will build the house at 206 Mckenzie St. Due to the small area, the road must be closed, and they need to demo the building safely. All detours will be set up starting Oct. 28 through June 30, 2025. The area will need to be fenced off from the public. All utilities and the curb in front of the property will be redone.  
Contact: rmgomez@santafenm.gov  

Click here for Guadalupe St. Reconstruction Project Updates.

Contractor: GM Emulsion and McDade-Woodcock
Location: Beckner Road and Richards Avenue
Project Description:  The City of Santa Fe’s contractors continue to make progress on the intersection improvements.  Temporary Traffic Control at the Beckner and Richards Ave intersection will remain in place through the completion of the project with restricted left turns at that intersection.  Through Friday, Oct. 18, right turns from Richards Avenue onto Beckner Road will be prohibited for westbound traffic during reconstruction of the westbound lane and paving at the intersection.  A temporary detour will be in place for westbound Beckner traffic from Richards at the intersection of Governor Miles.  A message board will be in place to notify motorists of the pending temporary closure of right turns at that intersection. Right turns at the intersection for Beckner westbound traffic will be reopened by the end of the day on Friday, Oct 18.

Contractor: GM Emulsion
Location: Nava Ade Trail between Governor Miles Rd. to Rodeo Rd.
Project Description: Portions of the Nava Ade Trail will be closed from Oct.15 to Oct.18 while GM Emulsion performs trail maintenance and patchwork. Suitable detours will be provided for closed areas.
Contact: Scott Overlie, saoverlie@santafenm.gov

Contractor: Franco’s Trees and Landscaping
Location: St. Francis to Paseo de Peralta
Project Description: Franco’s will do heavy tree-thinning in the Arroyo Mascaras. The work is anticipated to take two weeks. Portions of the walking trail may be closed for tree loading. Work began Oct. 5.
Contact: Jimmie Gallegos, jgallegos1@santafenm.gov

Contractor: Seeds of Wisdom
Location: West Alameda
Project Description: Seeds of Wisdom is thinning trees along the Santa Fe River from the Gonzales bridge to St. Francis. All trees being cut are invasive species. Temporarily, temporary access to the river trail will sometimes be provided for high-risk trees being cut. The trail would only be closed for a couple of hours, and all work would be done outside of school hours. Flagmen will be in place to direct traffic through the work zone when necessary. Work is anticipated to take a few weeks.
Contact: Jimmie Gallegos, jgallegos1@santafenm.gov