Disclaimer: The information in the Orange Barrel report is compiled based on the best available information and is subject to change without notice.

This page was updated on Friday, January 30, 2026, at 3:35 pm


 

NEW PROJECT

Contractor: Daniel’s Landscaping

Location: Galisteo Road

Description: Daniel’s Landscaping will be cleaning dead and down debris dumped in the Arroyo de los Pinos below Galisteo Road. Work is expected to take 1-2 days, starting on 1/28. There will be no impact on traffic.

Contact: Jimmie Gallegos,  jgallegos1@santafenm.gov

 

NEW PROJECT

Contractor: GM Emulsion  

Location: Airport Rd

Description: Road rehabilitation project from 599 to Cerrillos Rd.  

Initial work includes removing and replacing concrete ADA curb ramps and other various concrete structure work. Weather permitting, work is scheduled to begin on 2/11/26 and is expected to be completed by the end of May 2026. Traffic control shall be in place during the duration of the project. Motorists are encouraged to seek alternate routes when possible.

Contact: Apollo Hernandez, ajhernandez@santafenm.gov

 

NEW PROJECT

Contractor: Gonzalez Concrete  

Location: 5981 Airport Rd

Description: Remove and replace sidewalk, curb, and gutter. Work is scheduled to begin on 1/4/26 and is expected to take 2 weeks to complete. Traffic control shall be in place. Motorists are advised to seek alternate routes when possible.

Contact: Apollo Hernandez, ajhernandez@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: GM Emulsion

Location: Old Pecos Trail from Cordova Rd to Calle Medico.

Description: Remove and replace ADA sidewalk ramps. Weather permitting, work is anticipated to take 3 weeks. Traffic control signage with intermittent flaggers will be in place.

Contact: Apollo Hernandez, ajhernandez@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: GM Emulsion

Location: 2530 W. Alameda St.

Description: Arroyo structure outfall repairs. Work is anticipated to take 2 Months. Traffic  

Control Signage will be in place. Proceed with caution.

Contact: Apollo Hernandez, ajhernandez@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: Gonzalez Concrete Construction

Location: Pablina St at Cam. Sierra Vista

Description: Remove and replace ADA sidewalk ramps and Valley Gutter. Weather permitting, work is scheduled to begin on 1/27/26. Work will be done intermittently and is anticipated to take 4-5 weeks to complete. Traffic control shall be in place during the duration of the project.

Contact: Apollo Hernandez, ajhernandez@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: Full Circle. No work from 12/20-1/2/2026.  

Location: Arroyo Mascaras from St. Francis to Guadalupe  

Description: There will be a strategic thinning of invasive elms and trash removal in the arroyo. Work started December 12, 2025, and is anticipated to take 4-6 weeks.  

Contact: Jimmie Gallegos, jgallegos1@santafenm.gov  

 

PROJECT ONGOING AS SCHEDULED

Contractor: EMCO of Santa Fe, LLC.  

Location: Calle Angelina from 1504 to 1562.  

Description: Calle Angelina Road has been recently repaved. The project requires some minor finishing touches, which are expected to conclude within the next two weeks. Please proceed with caution.

Contact: Apollo Hernandez, ajhernandez@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: GM Emulsion  

Location: Tierra Contenta Trail, between Sweeny Elementary and Ortiz Middle School.  Description: Construction of a new ten-foot-wide bike and pedestrian trail, erosion control, and stormwater treatments began in August. The new trail will connect Ave Contenta to South Meadows Rd via a new trail extension. Work is expected to be complete in the summer of 2026.  

Contact: Kody Keelin kwkeelin@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: EMCO of Santa Fe  

Location: Agua Fria & South Meadows  

Description: This project was initiated in response to residents’ requests to address failing traffic signals at the intersection of Agua Fria and South Meadows, driven by rapidly changing land use in the area. The project includes intersection upgrades, new traffic signals, and added turning lanes to improve safety, traffic flow, and achieve NMDOT Level of Service (LOS) A, which represents the highest standard for minimizing delays and congestion.

Construction has taken longer than originally anticipated, and we sincerely apologize for the extended timeline. Delays are primarily due to long lead times for specialized signal equipment that must be custom-manufactured, along with broader supply-chain challenges and tariff impacts.


The new traffic signals are scheduled to be installed in February. Until that time, a temporary four-way stop will remain in place to maintain safe operations at the intersection. Motorists are encouraged to seek alternate routes when possible. We appreciate the community’s patience and understanding as we complete these important, long-term improvements.  

Contact: Kody Keelin kwkeelin@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: Daniel’s Landscaping & Construction  

Location: Buckman ATV/MX Track Prak, End of Chili Line Trail, and north of 599

Description: Installation of a water tank and pump house. No traffic flow disturbances, but the park will be closed. Work begins 11/17/2025 and is estimated to finish 02/.  

Contact: Carlos Saiz, crsaiz@santafenm.gov(505) 795-2556

 

PROJECT ONGOING AS SCHEDULED

Contractor: SF Brown Inc  

Description: Zia Station Public Infrastructure project.  

• Speed limit on Galisteo Rd. reduced to 25 mph between Zia Rd and Calle Luminoso

• LEFT turns from Galisteo to Zia Rd. are prohibited.

• Westbound Zia Rd. still reduced to a single lane between St. Francis Dr. and Candelero

• Sidewalk on the south side of Zia is open from Vela to St. Francis

• Sidewalk on the north side has been removed and is closed to all pedestrian traffic – please use the sidewalk on the south side of Zia.

• WATCH FOR TRUCKS/EQUIPMENT ENTERING AND EXITING ZIA ROAD TO/FROM ZIA FLATS APARTMENT PROJECT ON NORTH SIDE OF ZIA RD.

Contact: Merritt Brown, merritt@sfbrown.com, Albert Chavez, wachavez@santafenm.gov

 

 

PROJECT ONGOING AS SCHEDULED

Contractor: Seeds of Wisdom.  

Location: La Familia pedestrian bridge to Camino Alire along the north bank of the Santa Fe River.  

Description: Vegetation management of invasive species. There will be no impact on traffic. Work will begin on 11/4 and is anticipated to take approximately two to three months.

Contact: Jimmie Gallegos, jgallegos1@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: Seeds of Wisdom.  

Location: La Familia pedestrian bridge to Camino Alire along the north bank of the Santa Fe River. Description: Vegetation management of invasive species. There will be no impact on traffic. Work will begin on 11/4 and is anticipated to take approximately two to three months.

Contact: Jimmie Gallegos, jgallegos1@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: Sub Surface Contractor

Location: Camino Del Monte Sol and Camino Santander

Description: Sub Surface is contracted by the City Water Dept. To install new water lines from Garcia St. to Camino Del Monte Sol, down to Camino Santander. There will be road closures during the day as work is performed. Follow detour signs as directed. Residents will have access in and out of their homes, and emergency services will have access if needed. Work duration will continue on January 5th for a few months.  

Contact: Albert Chavez wachavez@santafenm.gov

 

PROJECT ONGOING AS SCHEDULED

Contractor: True North Builders LLC

Location: 206 Mckenzie

Description: 206 Mckenzie is closed due to a whole remodel of the building on Mckenzie. There is no room for all the workers on site. The road is closed for equipment, staging area, and stucco work on the building. All detours are in place, and traffic control is up. Due to break-ins on the property, this closure has helped with these issues. Once the weather warms up, the stucco will be completed. The project completion date is August.  

Contact: Cody North buildnorth@gmail.com  Ryan Gomez rmgomez@santafenm.gov