Project: Guadalupe Street Bridge Deck Rehabilitation
Category: Complete Streets
Phase: Construction
Goal: Mobility
Construction Start: September 11, 2023
Expected Completion: December 15, 2023
Fully Funded: $1,319,625
Location: Latitude 35.687270° Longitude -105.944014°
Description: Pavement rehabilitation of Guadalupe Street Bridge.
Project Scope: Remove and replace pavement surfaces of Guadalupe Bridge.

 