Project Title: Bishops Lodge Road Reconstruction
Project Description: Reconstruction of Bishop’s Lodge Road, including widening of the roadway within the existing ROW to incorporate multimodal transportation alternatives, including bicycle lanes and an adjacent trail. These amenities are being designed along with pavement and drainage improvements along the corridor. The design project extends from Callecita Pl. to the city limits with an initial studied length from Paseo Del Peralta to the city limits. The project is currently in the design phase.
Early Neighborhood Notification Meetings
- Public Meeting #1
- Santa Fe Convention Center, June 22, 2022 (5:30 – 7:30 PM)
- Public Meeting #2
- Santa Fe Convention Center, September 29, 2022 (5:30 – 7:30 PM)
- Public meeting 3
- Santa Fe Convention Center, June 17, 2024 (6:00-7:00 PM)
- Project Accomplishments to Date – Completed tasks
- Scoping report
- Design submittals (30%, 60%, 90%)
- Target Completion Dates
- Current stage: finalizing 100% percent drawings – Proposed submittal January 2025
- Final Submittal: Production Submittal Mid-March 2025
- Construction – Dependent on funding
Project Engineer: Luke Smith, PE Luke.Smith@wilsonco.com 505-348-4153 Wilsonco.com |
Project Manager Ania Pastuszewska, MBA, LEED AP Ania.Pastuszewska@nv5.com 970-426-2198 NV5.com |
Capital Projects Manager Romella Glorioso-Moss, PhD rsglorioso-moss@santafenm.gov 505-955-6623 City of Santa Fe |