Due to a water leak at the GCCC, the facility will be closed for the remainder of the evening. It is expected to reopen tomorrow morning at the normal time.

Design and engineering of Paseo del Sol Extension from its current western terminus at Jaguar Drive east to the Paseo del Sol/Herrera Drive roundabout, to be performed according to the Tierra Contenta Phase 3 Master Plan Amendment approved by the Governing Body in October 2021. The design effort includes the following elements:

  • Paseo del Sol extension and associated Paseo del Sol Loop roadways to include two travel lanes, bicycle lanes, and ADA-compliant sidewalks
  • Utilities - water, sewer, and dry utilities
  • Drainage improvements, including Drainage Study update
  • Streetscape landscaping
  • Street lighting
  • Surveying - topography and right-of-way dedication plat
  • Traffic Impact Analysis update
  • Geotechnical Investigation
  • Archaeology update
  • Design Standards (roadway typology and associated development guidelines)

 

  • Early Neighborhood Notification Meeting: December 15, 2022. Click here to view the presentation.
  • Project Accomplishments to Date:  Construction Documents are 90% complete.
  • Target Completion Dates:  Plans will be 100% complete Q1 2025.