Design and engineering of Paseo del Sol Extension from its current western terminus at Jaguar Drive east to the Paseo del Sol/Herrera Drive roundabout, to be performed according to the Tierra Contenta Phase 3 Master Plan Amendment approved by the Governing Body in October 2021. The design effort includes the following elements:

  • Paseo del Sol extension and associated Paseo del Sol Loop roadways to include two travel lanes, bicycle lanes, and ADA-compliant sidewalks
  • Utilities - water, sewer, and dry utilities
  • Drainage improvements, including Drainage Study update
  • Streetscape landscaping
  • Street lighting
  • Surveying - topography and right-of-way dedication plat
  • Traffic Impact Analysis update
  • Geotechnical Investigation
  • Archaeology update
  • Design Standards (roadway typology and associated development guidelines)

 

  • Early Neighborhood Notification Meeting: December 15, 2022. Click here to view the presentation.
  • Project Accomplishments to Date:  Construction Documents are 90% complete.
  • Target Completion Dates:  Plans will be 100% complete Q1 2025.