- Road Projects and Construction Updates
- Airport Road Repaving Project
- Agua Fria South Meadows
- Arroyo de los Chamisos Crossing
- Guadalupe Street Road Reconstruction
- Guadalupe Street Bridge Deck Rehabilitation
- Henry Lynch Road Reconstruction
- Bishop's Lodge Road Reconstruction Project
- St. Michael's Rail Trail Underpass
- Paseo del Sol Extension Project
- Traffic Engineering
- Street Maintenance
- Street Permits
-
Capital Projects Section
- Facility Management Division
- Parking
- Capital Improvements Advisory Committee
- Wastewater Management Permits and Data
Airport Road Repaving Project
Project Overview
The Public Works Department’s Complete Streets Division will be initiating the first phase of improvements to Airport Road, between Cerrillos Road and NM-599.
Construction is scheduled to begin February 11, 2026, and is anticipated to continue through the end of June 2026, weather and field conditions permitting.
Traffic control measures will be in place throughout the duration of the project. Motorists are encouraged to use alternate routes when possible and to allow extra travel time when traveling through the area.
Project Total Cost: $5,497,669.51
Funding Source: 2025 GO Bond: Road Improvements
Project Updates
Project Status at a Glance
- Construction continues at the South Meadows Road and Airport Road intersection on the southbound lane. Traffic can expect lane shifts at the intersection. Through traffic on both the northbound and southbound lanes of South Meadows Road will remain open.
- Concrete and asphalt work continues on both the north and south sides of Airport Road outside lanes from Cerrillos Road to Country Club Road. Work will be completed segment by segment, with each segment expected to take approximately 3–6 days depending on weather and field conditions.
- Each construction segment is expected to take approximately 3–6 days, depending on weather and field conditions.
Weekly Construction Update
Airport Road – Phase One Improvements
Week of March 16–20, 2026
The City of Santa Fe Public Works Department’s Complete Streets Division is continuing Phase One roadway improvements on Airport Road between Cerrillos Road and NM 599.
Planned Scope of Work – Week of March 16, 2026
- Construction at the South Meadows Rd and Airport Rd intersection will continue on the southbound lane. Traffic can expect lane shifts. Through traffic on both northbound and southbound lanes of South Meadows Rd will remain open.
- Construction continues at the Airport Rd and Zepol Rd intersection. Traffic can expect lane shifts. Both north and south access onto Zepol Rd will remain open.
- Construction at 4220 Airport Rd will require an outside lane closure. Traffic can expect lane shifts.
- Concrete work will take place on both the north and south sides of Airport Rd from Cerrillos Rd to Country Club Rd, completed segment by segment.
- Asphalt work continues on both the north and south sides of Airport Rd outside lanes from Cerrillos Rd to Country Club Rd.
- Each construction segment is expected to take approximately 3–6 days, depending on weather and field conditions.
Traffic Control – Week of March 16
Traffic control will be set up before any construction takes place, weather permitting.
- Traffic can expect outside (rightmost) lane closures on both the north and south sides of Airport Rd from Cerrillos Rd to Country Club Rd.
- Rightmost turning lane closure going north off Cerrillos Rd onto Airport Rd.
- Rightmost turning lane closure going south off Cerrillos Rd onto Airport Rd.
- Intermittent lane closures at intersections for paving operations.
- Outside lane closure at 4220 Airport Rd. Traffic can expect lane shifts.
- Through lane closure at the Rodeo Rd and Airport Rd intersection onto Airport Rd.
- Traffic can expect lane shifts at the South Meadows Rd and Airport Rd intersection. Through traffic on both the northbound and southbound lanes of South Meadows Rd will remain open.
- Traffic can expect lane shifts on Zepol Rd. Both north and south access onto Zepol Rd will remain open.
Motorists are encouraged to use alternate routes when possible and allow extra travel time when traveling through the area.
The City will continue providing weekly updates and additional notices as work progresses. We appreciate the community’s patience and cooperation as we complete these important roadway and accessibility improvements.
Weekly Construction Update
Airport Road – Phase One Improvements
Week of March 9–13, 2026
The City of Santa Fe Public Works Department’s Complete Streets Division is continuing Phase One roadway improvements on Airport Road between Cerrillos Road and NM 599.
Planned Scope of Work – Week of March 9, 2026
- Construction continues at the South Meadows Rd and Airport Rd intersection on all three southbound lanes. This will require a road closure on South Meadows Rd from Rufina Rd to Airport Rd, with traffic detoured to Jemez Rd. The closure is expected to be in place from Monday through Wednesday.
- Concrete structure improvements will commence 03/10 at the Airport Rd and Zepol Rd intersection. Traffic can expect lane shifts. Both north and south access onto Zepol Rd will remain open.
- Asphalt work continues on both the north and south sides of Airport Rd turning/deceleration lanes from Cerrillos Rd to Country Club Rd.
- Each segment is expected to take approximately 3–6 days, depending on weather and field conditions.
Traffic Control – Week of March 9
Traffic control will be set up before any construction takes place, weather permitting.
- Traffic can expect rightmost lane closures on both the north and south sides of Airport Rd from Cerrillos Rd to Country Club Rd.
- Both north and south access onto Zepol Rd will remain open.
- Rightmost turning lane closure going north off Cerrillos Rd onto Airport Rd.
- Rightmost turning lane closure going south off Cerrillos Rd onto Airport Rd.
- Southbound road closure on South Meadows Rd from Rufina Rd to Airport Rd. Traffic will be detoured to Jemez Rd. The closure is expected to be in place from Monday through Wednesday.
- Through traffic on the northbound lane of South Meadows Rd will remain open.
Motorists are encouraged to use alternate routes when possible and allow extra travel time when traveling through the area.
The City will continue providing weekly updates and additional notices as work progresses. We appreciate the community’s patience and cooperation as we complete these important roadway and accessibility improvements.
Contractor: SRD Construction
Location: 4327 Airport Rd (Fronting the Vista Alegra Apartments.)
Description: Construction has been scheduled to begin on 3/4/26 through 3/10/26, weather and field conditions permitting. Traffic control shall be in place during the duration of the project. Motorists are encouraged to seek alternate routes when possible and to allow extra time when traveling through the area.
Contact: Scott Healy, 505-362-9614, healyscott15@gmail.com
Scope of Work:
- Sidewalk, curb and gutter improvements
Contractor: SRD Construction
Location: 4327 Airport Rd (Fronting the Vista Alegra Apartments.)
Description: Construction is scheduled to begin on 3/4/26 and anticipated to be completed on 3/9/26, weather and field conditions permitting. Traffic control shall be in place during the duration of the project. Motorists are encouraged to seek alternate routes when possible and to allow extra time when traveling through the area.
Scope of Work:
- Sidewalk, curb and gutter improvements
Weekly Construction Update
Airport Road – Phase One Improvements
Week of March 2–6, 2026
The City of Santa Fe Public Works Department’s Complete Streets Division is continuing Phase One roadway improvements on Airport Road between Cerrillos Road and NM 599.
Schedule Update
Construction is anticipated to continue through the end of May 2026, weather and field conditions permitting.
Planned Scope of Work – Week of March 2, 2026
- Concrete work continues on the north side of Airport Rd, moving west toward Country Club Rd, segment by segment, with asphalt milling to follow as weather allows.
- The southbound turning lane from South Meadows Road onto Airport Road will be closed due to construction at the South Meadows Road and Airport Road intersection. Through traffic on South Meadows Road will remain open. Motorists who need to turn onto Airport Road southbound should use Jemez Road as a detour. The detour is expected to be in place from Monday through Wednesday.
- Traffic will be detoured through Jemez Road, and the detour is expected to last from Monday through Wednesday.
- Each segment is expected to take approximately 3–6 days, depending on weather and field conditions.
Additional Scope Item
An additional task has been added to the overall scope: traffic signal loop detection repairs following the pavement striping task.
Traffic Control – Week of March 2
Traffic control will be set up before any construction takes place, weather permitting.
- Traffic can expect right lane closures from Cerrillos Rd going west to Country Club Rd.
- Possible right-turn lane closure off Cerrillos going north onto Airport Rd.
- Possible right-turn lane closure going south off Cerrillos onto Airport Rd.
Motorists are encouraged to use alternate routes when possible and allow extra travel time when traveling through the area.
The City will continue providing weekly updates and additional notices as work progresses. We appreciate the community’s patience and cooperation as we complete these important roadway and accessibility improvements.
Weekly Construction Update
Airport Road – Phase One Improvements
Week of February 23–27, 2026
The City of Santa Fe Public Works Department’s Complete Streets Division is preparing to begin Phase One roadway improvements on Airport Road between Cerrillos Road and NM 599.
Schedule Update
The initial start date has been moved back to February 23 due to inclement weather expectations.
Construction is anticipated to continue through the end of May 2026, weather and field conditions permitting.
Planned Scope of Work
Phase One focuses on the segment from Cerrillos Road to Fairly Road and includes:
- Removal and replacement of ADA-compliant curb ramps
- Associated concrete and sidewalk improvements
- Asphalt paving to follow concrete work, weather permitting
Work Sequence
- Concrete work will begin on the north side of Airport Road, starting at Cerrillos Road and moving west toward Country Club Road, segment by segment.
- Once the northern segments are complete, crews will shift to the south side of Airport Road and move east back toward Cerrillos Road.
- Each segment is expected to take approximately 3–6 days, depending on weather and field conditions.
As concrete work is completed in each segment, asphalt paving will follow as temperatures and weather allow.
Traffic Control – Week of February 23–27
Traffic control will be set up prior to construction activities, weather permitting. The following lane closures are anticipated during initial setup and construction:
- Center lane closure on Rodeo Road moving west toward the Cerrillos Road intersection
- Left lane closure on Airport Road from Cerrillos Road extending through the active construction segment
- Left-turn lane closure off Cerrillos Road northbound onto Airport Road
- Inside turn lane closure southbound off Cerrillos Road onto Airport Road
Motorists are encouraged to use alternate routes when possible and allow extra travel time when traveling through the area.
The City will continue providing weekly updates and additional notices as work progresses. We appreciate the community’s patience and cooperation as we complete these important roadway and accessibility improvements.
Weekly Construction Update
Airport Road – Phase One Improvements
Week of February 16–20, 2026
The City of Santa Fe Public Works Department’s Complete Streets Division is preparing to begin Phase One roadway improvements on Airport Road between Cerrillos Road and NM 599.
Schedule Update
The initial construction start date has been adjusted due to the Underground Utility Line location approval timeline.
- Revised start date: Thursday, February 19, 2026
- Possible early start: If utility line location is approved by February 17, the contractor will begin construction setup on February 17.
Construction is anticipated to continue through the end of May 2026, weather and field conditions permitting.
Planned Scope of Work
Phase One focuses on the segment from Cerrillos Road to Fairly Road and includes:
- Removal and replacement of ADA-compliant curb ramps
- Associated concrete and sidewalk improvements
- Asphalt paving to follow concrete work, weather permitting
Work Sequence
- Concrete work will begin on the north side of Airport Road, starting at Cerrillos Road and moving west toward Country Club Road, segment by segment.
- Once the northern segments are complete, crews will shift to the south side of Airport Road and move east back toward Cerrillos Road.
- Each segment is expected to take approximately 3–6 days, depending on weather and field conditions.
As concrete work is completed in each segment, asphalt paving will follow as temperatures and weather allow.
Traffic Control – Week of February 16–20
Traffic control will be set up prior to construction activities, weather permitting. The following lane closures are anticipated during initial setup and construction:
- Center lane closure on Rodeo Road moving west toward the Cerrillos Road intersection
- Left lane closure on Airport Road from Cerrillos Road extending through the active construction segment
- Left-turn lane closure off Cerrillos Road northbound onto Airport Road
- Inside turn lane closure southbound off Cerrillos Road onto Airport Road
Motorists are encouraged to use alternate routes when possible and allow extra travel time when traveling through the area.
The City will continue providing weekly updates and additional notices as work progresses. We appreciate the community’s patience and cooperation as we complete these important roadway and accessibility improvements.
Upcoming Roadway Improvements on Airport Road
The City of Santa Fe Public Works Department’s Complete Streets Division will initiate Phase One roadway improvements on Airport Road between Cerrillos Road and NM 599.
The project will be completed in two phases. Phase One will focus on the segment from Cerrillos Road to Country Club Road and will include concrete and accessibility improvements followed by asphalt work, as weather conditions allow.
Initial Construction Activities
Phase One construction will begin with concrete work, including:
- Removal and replacement of ADA-compliant curb ramps
- Associated concrete and sidewalk improvements
Construction is scheduled to begin February 11, 2026, and is anticipated to continue through the end of May 2026, weather and field conditions permitting.
Where Work Will Begin and How It Will Progress
Initial concrete work will begin on the north side of Airport Road, starting at Cerrillos Road and moving westward in the following order as each section is completed:
- Cerrillos Road to Zepol Road
- Zepol Road to Jemez Road
- Jemez Road to South Meadows Road
- South Meadows Road to Paseo del Sol
- Paseo del Sol to Fairly Road (turnaround point)
Once work reaches Fairly Road, construction will change direction and move to the south side of Airport Road, progressing eastward in the following sequence:
- Fairly Road to Paseo del Sol
- Paseo del Sol to South Meadows Road
- South Meadows Road to Jemez Road
- Jemez Road to Zepol Road
- Zepol Road to Cerrillos Road
Initial work will continue along the north side of the roadway, moving west as each individual segment is completed, before transitioning to the south side.
Work Duration at Specific Locations
Construction activity is expected to take approximately 3–6 days per segment, depending on site conditions and weather. More precise timeframes will be provided once work begins and crews establish a production pace.
Asphalt Work
As concrete work is completed in each section, the City plans to transition directly to asphalt work, weather permitting. Asphalt paving will begin once temperatures meet required conditions and concrete work is complete.
Traffic Impacts and Updates
Traffic control measures will be in place throughout the project. Motorists are encouraged to use alternate routes when possible and to allow extra travel time when traveling through the area. The City is committed to providing frequent updates as work progresses, including daily updates if necessary. Project staff will meet weekly to review schedules and ensure the most accurate and up-to-date information is shared with the public. We appreciate the community’s patience and cooperation as we complete these necessary improvements to roadway safety and accessibility.
Contractor: Gonzalez Concrete
Location: 5981 Airport Rd
Description: Sidewalk, curb, and gutter improvements. Work is scheduled to begin on 2/5/26 and is anticipated to take 3 weeks to complete. Traffic control measures will be in place. Motorists are advised to seek alternate routes when possible.
Scope of Work:
- Concrete curbs, gutters, and sidewalk improvements
Construction Phasing and Schedule:
The project will be completed in two phases, both phases having two major tasks assigned.
Phase 1: Cerrillos Road to Country Club Road
Estimated Start: February 11, 2026
Estimated Completion: End of April 2026
Project Area
North and south sides of Airport Road between Cerrillos Road and Country Club Road
Task 1: Concrete Work
Scope of Work
- Removal and replacement of ADA-compliant curb ramps
- Concrete improvements including curbs, valley gutters, and sidewalks
Construction Sequence
- Concrete Work (A):
North side of Airport Road, starting at Cerrillos Road and moving west to Country Club Road - Concrete Work (B):
South side of Airport Road, starting at Country Club Road and moving east to Cerrillos Road
Task 2: Asphalt Work
Scope of Work
- Asphalt road rehabilitation
- Asphalt striping and pavement markings
- Traffic signal detection loop repairs
Construction Sequence
- Begins after all concrete work is completed
- Asphalt Work (A):
From Cerrillos Road moving west to Country Club Road - Asphalt Work (B):
From Country Club Road moving east to Cerrillos Road - Final pavement markings and striping to follow
Potential Delays
- Inclement weather
- Unexpected underground utility issues
Airport Road Phase 1 Construction Area
Phase 2: Country Club Road to NM 599
Estimated Start: March 9, 2026
Estimated Completion: End of May 2026
Project Area
North and south sides of Airport Road between Country Club Road and NM 599
Scope of Work – Same as Phase 1
- Removal and replacement of ADA-compliant curb ramps
- Concrete improvements including curbs, valley gutters, and sidewalks
- Asphalt road rehabilitation
- Asphalt striping
- Traffic signal detection loop repairs
Potential Delays
- Inclement weather
- Unexpected underground utility issues
Coordination With Private Development:
Some private businesses along Airport Road will be updating sidewalks and driveways in coordination with this project. These improvements are associated with the overall construction activity but are not City projects. The City will clearly identify these locations to help the public understand the distinction.
Stay Informed
Project updates, notices, and timeline changes will be shared throughout construction. Residents, commuters, and businesses are encouraged to sign up for City notifications or check back regularly for the latest information.