Project Update: September 12, 2025
We’re pleased to share that the Guadalupe Street Reconstruction Project is nearing completion. Our team is actively working through the punch list items identified during the joint inspection with NMDOT and FHWA on August 27.
This includes final tasks such as signage installation and roadway striping. We anticipate completing the striping next week, which will mark a significant milestone toward wrapping up the project.
Thank you for your continued support and patience as we finalize this important improvement for our community!

Guadalupe Street Road Reconstruction
Category: Complete Streets Capital Projects
Phase: Construction
Goal: Mobility
Construction Start: December 15, 2023
Projected Completion: Summer 2025
Fully Funded: $10,286,157
Description: Reconstruction of Guadalupe Street from Agua Fria to Paseo de Peralta.
Project Scope: Reduce travel lanes from four to three. Construct medians, ADA-compliant sidewalks, and bicycle lanes. Improve stormwater drainage and intersection geometrics at West Alameda Street, West San Francisco Street, Catron Street, and Paseo de Peralta.